News Flash Home
The original item was published from 12/18/2015 2:28:00 PM to 1/1/2016 12:00:02 AM.

News Flash

Public Works

Posted on: October 14, 2015

[ARCHIVED] First Phase of Road Construction / UPDATE All Streets Completed (12.15.15)

Twinleaf AFTER

The City of Castle Hills contractor, Clark Construction, and their sub-contractors have been working to improve the roadways in our city. The roadway repairs consisted of removing and replacing asphalt.

Construction began on the first street on September 30th, 2015. All streets in this phase were completed by December 15th, 2015.

HALBART DR - from Northcrest Dr to Northcrest Dr
HONEYSUCKLE LN - from Loop 410 to Lou Jon Cir
TWINLEAF LN - from Travertine Ln to Gladiola Ln
GLADIOLA LN - from Dandelion Ln to Towne Vue Road
HERWECK DR - from Danube Dr to Waydele Cir
TAMWORTH DR - from Lockhill Selma to NW Military Hwy

We appreciate your patience and cooperation during the construction phase. The City is excited to have completed these long awaited street repairs.

Stay tuned for the next phase of repairs to be posted soon.

Facebook Twitter Email